The San Antonio Court of Appeals has substantially reduced a multi-million judgment in a breach of contract case involving modification of a private aircraft.

Gulf View Private Investment, Inc. f/k/a Whitesell International, Inc., Neil Whitesell, Vincent Constantino, Adam Arters, Innova Aerospace Service & Support, LLC and Sierra Industries, LLC v. GC System, A.S. (No. 04-23-00100-CV; October 16, 2024) has a lengthy and somewhat complicated fact pattern that can be briefly summarized as follows. In 2016 GC, a Czech company, bought a 1977 Cessna Citation from Petr Mara for $500,000. In May 2016, Mara, acting on behalf of GC, executed five proposals for modifications of the aircraft, for which GC paid Sierra just over $1 million as an advance. Sierra was to perform the work at its facility in Uvalde and promised completion by January 2017. In the background of the primary transaction, Whitesell and a non-party, Huffstutler, negotiated a 50-50 ownership deal for Sierra. Gulf View, through Constantino and Arters, provided management services for Sierra.

In the event, Sierra fell way behind  and did not complete the modifications as promised. The parties met in March 2017 and agreed to push back the completion date to July 2017. Sierra didn’t meet that deadline, either, and there is evidence in the record that Sierra knew in March that it couldn’t meet it. At the same time, another entity, Innova, assumed Sierra’s contractual obligations, including modification of the Cessna. In November 2017, Whitesell ceased financing for Innova, which closed its doors. GC demanded that Innova transfer the Cessna to another modifier, Lancair, but had to get a court order to force Innova to do it. Lancair transferred the Cessna to a European modifier, which eventually returned it to GC in April 2021.

In 2018 GC sued Defendants for breach of contract, statutory violations, negligence, fraud, and negligent misrepresentation. The trial court granted partial summary judgment for GC against Sierra and Innova for breach of contract on three of the five modifications but did not rule on damages, attorney’s fees, or any of GC’s other claims. Those claims were tried to a jury, which for the most part found for GC. The jury awarded GC both out-of-pocket damages of $1,036,428, mitigation damages of $6.6 million, just over $1 million in statutory damages under the Texas Theft Liability Act, $200,000 on the negligence claim, $345,387 on the negligent misrepresentation claim, and $750,000 on the fraud claim. The trial court entered judgment largely on the verdict, except that it awarded no mitigation damages. Defendants appealed.

In an opinion by Chief Justice Martinez, the court of appeals affirmed in part, affirmed as modified in part, reversed and rendered in part, and remanded. Defendants argued legal sufficiency, so the court engaged in a detailed analysis of the evidence. The court reversed the trial court’s judgment awarding TTLA damages, holding that Whitesell’s alleged use of GC’s advance to pay other debts did not support a derivative liability claim under Texas law. The court likewise absolved the Whitesell Defendants of liability for GC’s negligence claim stemming from alleged hail damage to the Cessna, but overruled Innova’s legal sufficiency challenge on that claim, as well as on GC’s claim that Innova negligently lost the Cessna’s log books and other materials. However, the court remanded for new trial on damages for Innova’s negligence. Next, the court upheld Whitesell’s sufficiency challenge to the fraud claim but rejected Innova’s, where it found that the jury could reasonably have concluded that Innova knew it couldn’t meet the rescheduled deadline for delivery of the Cessna when it agreed to do so. The court reached the same result on the negligent misrepresentation claim, absolving Whitesell but overruling Innova’s sufficiency challenge. Finally, at to the TUFTA claim, the court concluded that there was evidence that Innova committed at least four badges of fraud out of the 11 badges listed in the statute. Finally, the court refused to pierce the corporate veil with respect to Whitesell’s relationship to Innova, holding that Whitesell did not directly and personally benefit from the fraud committed by Innova.

The upshot of the court’s lengthy analysis (the opinion runs to 69 pages) was to dismiss the Whitesell Defendants from the case but substantially keep Innova in it. The question then became whether the judgment violated the one-satisfaction rule. As discussed above, the judgment awarded out-of-pocket damages for breach of contract, as well as damages for GC’s TTLA claim. The court determined that some of the TTLA damages (for the hail damage) was encompassed by the breach of contract damages and thus barred by the one-satisfaction rule. But the TTLA damages for the lost logbooks and other materials were not so barred. Innova then attacked the trial court’s judgment on GC’s negligence, negligent misrepresentation, and fraud claims on the basis of the economic loss rule (i.e., damages for delay). Here the court found again that damages for the lost logbooks did not arise from delay, but the damages for negligent misrepresentation and fraud did. Finally, the court reversed the trial court’s award of GC’s attorney’s fees (since Innova did prevail on some of its issues) and remanded for new trial on the remaining attorney’s fees claims.

The court affirmed only the breach of contract out-of-pocket damages (the advance payment to Sierra of just over $1 million) and $464,000 for the lost items and engine damage. It remanded the TTLA and negligence parts of the judgment for new trial, as well as GC’s attorney’s fees. This opinion (as well as this summary) is long and sometimes tedious, yet important with respect to its evidentiary analysis, treatment of duplicative claims, application of the one-satisfaction and economic loss rules, and corporate law findings. It also demonstrates how careful and deliberate Texas intermediate courts are when faced with complex appeals. Too frequently judges are evaluated based on their partisan affiliation and not for their actual work. God forbid we ever follow that path here.

Pin It on Pinterest

Share This